Ask five founders what their first collection cost and you will get five numbers that cannot be compared, because none of them includes the same things. One counts samples, one does not. One counts duty, one finds out at the port. One counts the photography, one treats it as marketing.

The number that matters is not “what does a collection cost”. It is “which lines are in the budget, and which of them are fixed before the first PO”. This article is about the manufacturing side of that list, with the ranges you should expect to replace with real quotes.

The four manufacturing lines

Line What it covers When it is spent What founders usually get wrong
Development Tech pack, swatches, fit samples, revisions Before any bulk order Budgeting one sample round when two is normal
Production Yarn, knitting, making, trims, packing at MOQ At PO, with a deposit Assuming MOQ is negotiable; it usually is not below a certain point
Compliance Labels, care instructions, testing where required Before bulk, after the sample is approved Ordering labels before the care route is fixed
Logistics and duty Freight, insurance, customs, delivery After production, before delivery Forgetting that duty is charged on the goods value, not the margin

A worked example, with placeholders

The numbers below are illustrative planning figures, not a quotation from any factory. Replace each one with a real quote; the structure is the point.

Item Assumption Illustrative cost
Style development (one knit style) Tech pack + 1 swatch + 2 sample rounds €600–1,200
Bulk production 300 pcs × €32 FOB €9,600
Labels and trims Woven main label, care label, hangtag €400–800
Testing Fibre content, colourfastness, dimensional stability €300–600
Freight and duty Sea freight plus duty at 8–12% plus clearance €1,500–2,500
Total, one style at 300 pcs ≈ €12,400–14,700

Two things follow. The per-piece landed cost is not the FOB price: it is roughly 25–40% higher once freight, duty and the development cost spread over 300 pieces are included. And the development cost does not scale with quantity — it is the same whether you make 300 or 3,000, which is why a second style is cheaper per piece than the first.

Four fleece-back sweatshirts in green, tan, grey and black on a rail
Fleece weight drives the cost: 300 g and 440 g are different products.

Where the money actually leaks

  1. Sample rounds. One round is optimistic. Two is normal. Three happens when the measurement state was never agreed.
  2. Yarn substitution. A stock shade that is close but not right leads to a dye lot, which leads to a minimum you did not budget.
  3. Labels ordered too early. Care content changes after the first wash test, and the labels are already printed.
  4. Freight mode. Air freight for a first order is sometimes necessary and always expensive; it can add more than the duty does.
  5. Chargebacks. A retailer deduction for a labelling or packing miss is a cost that never appeared in the budget.

The cash-flow timeline matters more than the total

A first collection is usually paid for before it is sold. The sequence looks like this:

Stage Cash out Typical timing
Development Sample and swatch costs Weeks 1–6
PO deposit 30–50% of production Week 6–8
Balance Remaining production cost Before shipment
Freight and duty Landed cost At import
Retail payment Wholesale invoice 30–60 days after delivery, if wholesale

That gap — cash out at week 6, cash in at week 20 or later — is what closes small brands, not the unit cost. Plan working capital for the gap, not for the invoice.

What changes the number most

  • Number of styles. Each style carries its own development cost; three styles at 300 pieces cost more than one style at 900.
  • Yarn choice. Stock yarn in a stock shade is the cheapest path; a custom dye lot adds both cost and a minimum.
  • Structure. A plain jersey knit is cheaper than a cable or jacquard at the same gauge.
  • Terms. FOB gives you the duty line but usually a lower unit price; DDP bundles it and hides the split.
  • Timing. Rushing production into air freight can add 15–25% to landed cost.

Our low-MOQ capsule guide covers the order structures that keep the first buy small, and the services overview sets out what sits in the development phase versus production.

A decision table for the first budget

If this is true Do this Because
Budget under €15k One style, 300 pcs, stock yarn, simple structure Development cost is fixed; spreading it over more styles multiplies it
Launch date under 12 weeks Confirm yarn availability before design Yarn lead time is the constraint, not sewing
Selling wholesale Budget for 60-day payment terms You pay the factory before the retailer pays you
Selling DTC Budget photography and packing, not just product The garment is only half of what the customer buys
Testing a category Sample first, buy second A sample costs a fraction of a wrong 300-piece order

FAQ

What is the minimum realistic budget for a first knitwear collection?

It depends on the market and the structure, but the fixed costs — development, labels, testing, freight — mean that below roughly 300 pieces per style the per-unit cost rises sharply. The honest answer comes from a quote against a real tech pack, not from a range online.

Should I include marketing in the manufacturing budget?

No, keep them separate, but do not forget it. Photography, samples for content, and packing for DTC are real costs that sit outside the factory invoice.

Is it cheaper to order more pieces?

Per piece, usually yes, because yarn and machine set-up spread across more units. In total, no — and unsold stock is the most expensive outcome of all.

How much should I hold back as a buffer?

Ten to fifteen percent of the landed cost is a reasonable planning buffer for a first order, because one extra sample round or one air-freight decision can consume it.

Sources: ICC Incoterms 2020 and WCO HS nomenclature for the duty and classification side of the landed cost.

If you have a target budget, send it with the style and the launch date. We will tell you what fits inside it and what has to wait for the second order — that conversation is cheaper than a wrong PO.